Wednesday, December 1, 2010

Construction Update

As of December 1, 2010 Parrish Hall is 28 percent complete. The first floor slab for the entire building is done and the structural steel for part of the building has been erected. In the coming months the remaining structural steel frame will be completed, as well as the concrete decks and the masonry walls for the stairwells. Further updates on the construction of Parrish Hall to come...